Lantian Theater Reconstruction in Qingyu village, Shaanxi province 2019-2021

Participating WZQ Team:The Hong Kong Polytechnic University, Xi'an University of Archoecture and Technology
No. of participants: 88 university students and mentors (Hong Kong and Mainland China)
Beneficiary villagers: 800

Project category: Stage reconstruction
Time:January 2019 - December 2021

 

  

Foundation Construction Acceptance - November 19, 2020

  • The team conducts on-site inspection and acceptance, inspects the space area and size in detail, and compares the data with the construction drawings to ensure the accuracy of the construction
  • Follow up the construction quality and meet the construction requirements
     

  

Foundation Construction Investigation - October 22-23, 2020

  • Mr. Zhou Tie Gang, Ms. Li Li Min and the student Mr. Ma Lie from Xi'an University of Archiecture and Technology, the staff of the Foundation Mr. Chang Zhu Qing led the Wu Zhi Qiao school teams to survey the site again and discuss the drainage difficulties encountered during construction
  • The team was divided into two groups to conduct surveys to gain a more comprehensive understanding of the local area; about 20 people were consulted during the two-day survey
     
  •   

Second Investigation - November 9-13, 2019

  • Based on the information collected in the first investigation, the WZQ team designed a plan for stage transformation
  • Propose design schemes and ideas, actively discuss with villagers to improve and develop the design, and communicate to make the team's design more suitable for the villagers' needs and expectations
     

  

First Investigation - April 3-7, 2019

  • The WZQ team inspected the environment, took photos for records, and performed measurements on the site
  • Face to face conversation with the villagers to learn about the local culture and their needs and preferences

 